Process and Construction
Engineering, construction and manufacturing processes in the station spaces of the Continuum
The production of the concrete diamonds rhombi for the continuum by
Heike Klussmann and netzwerkarchitekten would not have been possible
without research into material development and production processes. In
close collaboration with the manufacturer Schwab-Stein in
Baden-Württemberg new production processes were developed, making it
possible to produce panels with extreme geometries that do not require
additional structural bracing while achieving a high degree of precision
and surface quality. The emphasis was above all especially even
surface, acute angles and precise edges.
Precast fair-faced concrete
sections are generally produced using formwork. This means concrete is
poured into prefabricated casings as a hollow form where the casing side
is visible and the filled side is to the back of the finished piece.
Because this method only makes sense when it is used for a large
quantity of identical elements, a different approach was used for the
realization of continuum.
All of the 6700 individual diamonds of
continuum were cut from blank slabs and produced with a vacuum filter
molding method. The mixture consisted of high-performance concrete,
aggregates of Nordic white and quartz sand and, for the pigment, 130
grams of black iron oxide per 100 kg of raw mixture. It was only
possible to produce the light color with complete consistency using the
specially developed mixture: cement and aggregates with a precise amount
of added pigment. Then, the basic mold (244 x 123 cm) was filled with
the raw mixture, leveled and homogenized, so that the material was
evenly spread throughout.
The homogenized raw slab then went to the
concrete slab press (a 65-ton press, the largest in the world) and was
pressed or rather compressed with a force of 3,000 tons per minute; in
the process, up to 50% of the water was removed. This was followed by a
hydraulic hardening process in optimum climatic conditions over two
days. The back of the highly compacted base slabs was then calibrated
and milled on the surface so that flatness tolerances in accordance with
DIN V 18500 were achieved.
Continuum, production of slabs for wall design, photo: Boris Trenkel
After another storage period to achieve
the final hardness, the slabs were cut and reworked. At this point, the
diamonds for the Continuum were positioned using a photo supported
detection system to use as much of the plates as possible and then a
5-axis CNC saw cut the slabs into the individual diamonds. Finally, the
edges were profiled and four anchor holes were drilled into the back of
each diamond panel.
In order to form the edges a special scheme was
designed to guarantee that inspection requirements would be met.
Classification as “bottom” or “top” fold panels meant that entire area
of the building shell remained accessible and each individual diamond
panel could be removed. At the same time, joints required no sealants
and the mounting remained invisible.
The minimal waste that was
created was 100% recycled and reused as aggregate. The surface of the
panels was then finished by applying a water-repellant coating and
anti-graffiti protection.
However, the extremely high standards
applied not only to the precast concrete sections, but also to the
substructure and its installation. “Clasps” that were invisible from the
front were attached to the back of the panels with an undercut drilling
method. They were then inserted into mounting rails. Because of fire
safety regulations and the low melting point of aluminum, it was not
possible to rely here on the customary commercial solutions and a
special system using stainless steel was developed.
Assembly of vertical axes system for fixing the rhombi on curved wall surfaces, photo: netzwerkarchitekten
Working model, "shearing" the rhombi when attached to curved wall surfaces, photo: netzwerkarchitekten
One exceptional
challenge was the installation of the concrete diamond panels in the
areas where the walls curved. Here, the wall panels take the shape of a
small-sectioned polygonal line following the ideal line of a circle
segment along the station walls. Because the diamond pattern has no
vertical joints, support posts were placed on the nodes of the regular
polygonal line frame to avoid the diamond tips getting out of line.
Thus, a high level of precision in the overall construction was achieved
through the dimensional accuracy of the panels and joints combined with
a minutely adjustable frame.
Continuum, Cut of the rhombi from the rough slabs for the wall, photo: Boris Trenkel
Back to top